Skip to main content

Irvine Ranch Water District RFP- MWRP Manhole Access

By January 10, 2018New Project Bids, RFP

Name of Project: Michelson Water Recycling Plant South Irvine Interceptor Sewer Manhole Access

Project Number: PR 07112, Code 7003
Project Manager: Malcolm Cortez, (949) 453-5854
Project Engineer: Harry Cho, (949) 453-5675
Design Engineer: Joseph Gutierrez, JIG Consultants, (714) 978-4407

Bidders: Bids will be accepted for this Project only from the prequalified bidders on the Project Bidders List. Prequalification to be placed on the Project Bidders List for this Project is closed.

Bid Opening Date: Wednesday, January 17, 2018, 2:00 PM

Location of Opening: Irvine Ranch Water District
15600 Sand Canyon Avenue, Irvine, CA 92618

Description of Project: The work includes the installation of a pre-packaged jetting unit adjacent to the subject manhole and construction of a 6-inch thick concrete slab with approximate dimensions of 9 feet by 15 feet. The concrete slab will be supported by a retaining wall against the landscaped slope. A concrete walkway with stairs and a single handrail will be constructed from the parking lot to the concrete slab to provide access to the jetting unit.

Plans/Specs: SABP) Reprographics
2372 Morse Avenue, Irvine, CA 92614 (949) 756-1001
KLD@sabp.com

Time of Performance: 200 consecutive calendar days from date of mailing the Notice of Award

Engineer’s Estimate: $173,100

Pre-Bid Meeting: A non-mandatory pre-bid meeting and site visit will be held at 9:00 AM
on Wednesday, January 3, 2018 at the IRWD Operations Center,
3512 Michelson Drive, Irvine, CA, 92612.