Costa Mesa Sanitary District RFP- Project No. 200-C
Force Main Replacement For South Coast Plaza Pump Station
Bids will be received by the Costa Mesa Sanitary District office at 628 West 19th Street, Costa Mesa, California until the hour of 10:00 a.m. on the 30th day of August, at which time they will be opened publicly and read aloud in the Board Conference Room. Sealed proposals shall bear the title of the project and the name of the bidder. Any bid received after the scheduled bid opening time shown above will not be accepted and returned to the bidder unopened. It shall be the sole responsibility of the bidder to seal and deliver the bid proposal to the District office at or before the time specified in this notice provided.
The Contractor shall comply with the provisions of the California Labor Code, the prevailing rate and scale of wages determined by the Director of the Department of Industrial Relations, State of California. Prevailing rates shall be paid to all workers employed in the performance of the contract. Such rates of wages are on file with Department of Industrial Relations and in the office of the District and are available to any interested party upon request. The contractor is responsible for all penalties prescribed for noncompliance to these provisions.
Each bid shall be submitted on the Bid Proposal Form furnished as part of the contract documents, and shall be accompanied by a certified check, a cashier’s check or a bidder’s bond in an amount not less than 10-percent of the amount of the bid, made payable to the Costa Mesa Sanitary District. The check or bond shall be given as guarantee that the bidder will enter into a contract with the District and furnish the required payment and performance bonds and certificates of insurance and endorsements if awarded the work. The check or bond will be declared forfeited if the successful bidder does not enter into the contract or furnish the required bonds and insurance forms under the time frame specified in the construction agreement.
There will be a mandatory pre-bid conference held on August 12, 2016 (Friday) at 10AM.
The meeting will begin at the District Engineer’s office: 234 East 17th Street, Suite 205, Costa Mesa CA 92627 (949) 548-1192.
It is imperative that the bidders carefully review this notice and the District’s standard construction agreement and insurance forms. The successful bidder will be required to comply with all requirements in the standard construction agreement and insurance forms. In the event of failure or inability to meet these requirements after the award of contract, the District shall have the right to reject the bid and/or declare a forfeiture of the bid bond.
Pursuant to California Contract Code Section 22300, CONTRACTOR will be entitled to post approved securities with the District or an approved financial institution in order to have the District release funds retained by the District to insure performance of the contract.
No bidder or subcontractor shall be listed in a bid proposal unless registered with the Director of Industrial Relations pursuant to Labor Code Section 1725.5.
Liquidated damages in the sum of $250 per day shall be imposed for each unexcused day beyond the contract completion date.
Plans and Specs available at:
SABP Reprographics, 2372 Morse Avenue, Irvine, CA 92614, (949) 756-1001 KLD@sabp.com