Contractor’s License classification “C-10” required for this project.
The majority of the work necessary for the completion of this contract consists of
Obtaining the City Building Permit;
Removing and disposing of existing generators
Clearing, grubbing, and preparing the sites
Constructing concrete pads and retaining curbs
Providing temporary power to the facilities as needed
Installing electrical conduits, switches, gears, and other necessary components
Procuring and installing back-up generators
Completing all required tests and certifications; and City Building Permit Final.
THE LOCATIONS WHERE THE WORK IS TO BE PERFORMED AND THE JOB WALK SCHEDULE ARE:
Date: April 27, 2015
9:00 AM at Central Library (1000 Avocado Avenue)
9:45 AM at Fire Station No.3 (870 Santa Barbara Drive)
10:30 AM at Lifeguard Headquarters (Newport Pier)
11:15 AM at Fire Station No.1 (110 E. Balboa Boulevard)
This will be the only opportunity for contractors interested in bidding the work to access the building interiors to take inventory of the required work.
Bid Documents, Project Specifications and Drawings Available at