Skip to main content

Irvine Ranch Water District Releases $1.1 Million RFP

IRWD Project: Lake Forest Zone B East Reservoir Floating Cover

Project Number: PR 10551

Project Manager: Malcolm Cortez, IRWD (949) 453-5854
Senior Engineer Harry Cho IRWD (949) 453-5675
Project Engineer: Alex Murphy, IRWD (949) 453-5863

Bidders: Bids will be accepted for this Project only from the prequalified bidders on the Project Bidders List. Prequalification to be placed on the Project Bidders List for this Project is closed.

Bid Opening Date: Thursday, January 17, 2019 at 2:00 pm.

Location of Opening: Irvine Ranch Water District, 15600 Sand Canyon Avenue, Irvine, CA 92618

Description of Project: This project will construct a new floating cover at the Lake Forest Zone B East recycled water reservoir. The reservoir is a 40,000 square foot concrete-lined open reservoir located in Lake Forest near the intersection of Regency Lane and Lake Forest Drive. Improvements will include construction of a chlorosulfonated polyethylene, weight tensioned floating cover and chafer, potable wash water line, drain line, asphalt concrete paving, and miscellaneous electrical improvements.

Plans/Specs Available at:
SABP Print Solutions
2372 Morse Avenue, Irvine, CA 92614 (949) 756-1001
Contact Kristen: kld@sabp.com

Time of Performance: 193 consecutive calendar days from date of mailing the Notice of Award.

Engineer’s Estimate: $1,099,800 (One million ninety-nine thousand eight hundred dollars)

Pre-Bid Conference: There will be non-mandatory pre-bid meeting on Thursday, December 20,
2018 at 9:00 am at IRWD Operations Center, 3512 Michelson Drive, Irvine, CA 92612 followed by a job walk at the Lake Forest Zone B East Reservoir.

IRWD Construction manual available for free download at www.irwd.com