The City of Lake Forest Releases New RFP- Improvement Project For Portola Parkway

The City of Lake Forest  Releases New RFP- Improvement Project For Portola Parkway

PROJECT NUMBER:  PW2013.13

photo

BID OPENING: May 24th  before 2:00 p.m. Sealed bids will be received  at the office of the City Clerk, 25550 Commercentre Drive, Suite 100.  At which time or thereafter said  bids  will  be  opened and  read  aloud.

NO PRE-BID CONFERENCE will be held for this project.

SCOPE OF WORK:

  • Project Mobilization and Demobilization
  • Traffic Control
  • Survey Services
  • Water Pollution Control Program
  • Clear and Grub
  • Unclassified/Roadway Excavation
  • Remove Concrete Curb & Gutter, AC Dike
  • Remove Concrete Median Paving & AC Median Paving
  • Remove Concrete Sidewalk
  • Remove Chain Link Fence
  • Construct Crushed Misc Base & Asphalt Concrete Pavement
  • Construct 8” PCC Curb and Gutter, PCC Sidewalk, Curb Access Ramp
  • Construct 6’ Chain Link Fence
  • Furnish & Install Irrigation System Sleeves & Install Topsoil
  • Construct Median Paving
  • Construct Irrigation System
  • Construct Soil Preparation & Fine Grading
  • Weed Abatement
  • Furnish & Plant Tree, Shrubs
  • Furnish & Install Mulch
  • Landscape Maintenance Period
  • Construct Reclaimed Irrigation
  • Service Facilities per IRWD plans
  • Furnish & Install Street Lighting System Conduit & Pullboxes per SCE plans & requirements
  • Furnish & Install Irrigation Controller Electrical System (SCE Conduits, Pullboxes, Pedestal, Electrical Conduit & Conductors,
  • Construct Traffic Signal
  • Modification
  • Pavement Signing, Striping & Markings

PROJECT MANAGER: Douglas A. Erdman, Principal Civil Engineer (949) 282-5233.

PLANS AND SPECIFICATIONS available at: SABP REPROGRAPHICS (949) 756-1001  KLD@sabp.com