Skip to main content

Irvine Ranch Water District Releases a Sewer Rehab RFP

Name of Project: Pelcan Hill Golf Club Sewer Rehabilitation

Project Number:Project Number 11121

Project Manager: Christian Kessler, 949-453-5441 kessler@ired.com

Engineer’s Estimate: $257,925.00

Time of Performance: 160 consecutive calendar days from date of mailing the Notice of Award

Bidders: Bids will be accepted for this Project only from the prequalified bidders on the Project Bidders List.  Prequalification to be placed on the Project Bidders List for this Project is closed.

Bid Opening Date: Monday, December 16, 2019, 2:00 PM PST (Electronic only)

Location of Opening: Irvine Ranch Water District, 15600 Sand Canyon Avenue, Irvine, CA 92618

Description of Project: Provide spill containment, temporary sewer bypass pumping, audio-video documentation, traffic control and mobilization and demobilization, pipeline cleaning, removal of failing epoxy lining, removal of calcium and removal of tree roots to facilitate the CIPP lining approximately 1,850 feed of 8-inch, 400 feet of 10-inch and 170 feet of 12-inch sewer pipeline, restoral of existing sewer laterals and restoral of damaged landscape.

Pre-Bid Conference: A mandatorypre-bid meeting is scheduled at 10:00 AM PST on Monday, December 2, 2019 at the IRWD Michelson Operations Center, 3512 Michelson Drive, Irvine, CA 92612, followed by project site visits.

 Plans/Specs Available from: SABP Print Solutions  2372 Morse Avenue, Irvine, CA 92614 (949) 756-1001

Contact Kristen at KLD@sabp.com