Skip to main content

Irvine Ranch Water District – Releases $8,000,000 RFP

By February 10, 2015New Projects, RFP

Irvine Ranch Water District

Releases $8,000,000 RFP

 

Name of Project: Peters Canyon Channel (F06) Water Capture and Reuse Pipeline

 

Project Number: PR 21163 (4985)

 

Bid Opening Date: March 12, 2015 at 2:00 PM

 

Location of Opening: Irvine Ranch Water District

15600 Sand Canyon Avenue, Irvine, CA 92618

 

Project Manager: Joe McGehee, 949-453-5542

 

Design Engineer: Tom Epperson, Tetra Tech, 949-809-5156

 

Pre-Bid Meeting: A mandatory pre-bid conference is scheduled for Wednesday, February 18,

2015 at 10:00 AM.  

The meeting will be at 15600 Sand Canyon Avenue, Irvine, CA 92618

Bidders:

Bids will be accepted for this Project only from the prequalified bidders Listed below 

ARB Inc

CCL Contracting

E.J. Myers Company

Flatiron Construction Corp.

Leatherwood Construction

Mladen Buntich Construction

Paulus Engineering

Steve Bubalo Construction

Sukut Construction

Sully Miller Contracting

Vido Artukovich & Sons

W.A. Rasic Construction

Plans

Description of Project: Construction of the Peters Canyon Channel (F06) Water Capture and Reuse Pipeline including buried piping, jack and bore at Como Channel, wet wells, meter vaults, valve vaults, desilting basin, diversion facilities, paving, concrete, electrical and telemetry equipment, submersible pumps, sampling equipment, and all other appurtenant work.

Plans/Specs Available:

SABP Reprographics

2372 Morse Avenue, Irvine, CA 92614 (949) 756-1001

IRWD Construction manual available for free download at www.irwd.com

2014-May_web1