IRWD- Chloramine Booster Stations at Foothill Zone 6 and Portola Zone 8 Reservoirs

By December 22, 2015New Project Bids

IRWD- New RFP- Chloramine Booster Stations at Foothill Zone 6 and Portola Zone 8 Reservoirs

Project Number: PR 11687 (4409)

Owner: Irvine Ranch Water District (IRWD) Engineering Department

Project Manager: Malcolm Cortez, (949) 453-5854

Project Engineer: Alex Murphy, IRWD (949) 453-5863

Design Engineer: Joseph Long, AECOM (714) 567-2725

Pages from PR 11687 Chloramine Booster Station Foothill ZN 6 and Portola ZN 8 Reservoirs Plans

Bidders: Bids will be accepted for this Project only from the prequalified bidders on the Project Bidders List. Prequalification to be placed on the Project Bidders List for this Project is closed.

  • ARB, Inc.
  • Clarke Contracting Corp
  • Steve P. Rados, Inc.
  • J.F. Shea Construction, Inc.
  • Archer Western Contractors
  • Stanek Constructors
  • Gateway Pacific Contractors inc.
  • Pascal $ Ludwig Constructors
  • Olsson Construction
  • Pacific Hydrotech
  • SS Mechanical Corp.
  • M Lyles Co.

Bid Opening Date and Time: Wednesday, February 3, 2016 2:00 PM PST

Location of Opening: Irvine Ranch Water District, 15600 Sand Canyon Avenue, Irvine, CA 92618

Description of Project: This project will construct chloramine booster stations and reservoir mixers at the Foothill Zone 6 and Portola Zone 8 domestic water reservoirs located in Foothill Ranch and Portola Hills.

Time of Performance: 360 consecutive calendar days from date of mailing the Notice of Award

Engineer’s Estimate:One million six hundred sixty-six thousand nine hundred dollars ($1,666,900)

Pre-Bid Meeting: A non-mandatory pre-bid meeting will be held on Tuesday, January 5, 2016 at 10:00 a.m. at IRWD Headquarters, 15600 Sand Canyon Avenue, Irvine, CA 92618.There will be a job walk following the meeting at the construction site.

Plans/Specs Available at: SABP Reprographics, 

2372 Morse Avenue, Irvine, CA 92614 (949) 756-1001